We continue to make great progress at The Mason Block site.

The roof is about 80 % complete and the window installation has just begun. We are expecting the entire building to be “dried in” within the next two weeks. We cant complain about the weather, Mother Nature has smiled upon us and helped us to stay on schedule. The view from the roof top decks is second to none and makes us all feel a little sad to say good bye to summer. Once the windows are installed we will look forward for the masonry work to begin as the Mason Block begins to take its final form. Stay tuned for future updates!